Earned value management: follow a €200k project
Follow a €200k warehouse-system project through planned value, earned value and actual cost. Calculate CPI, SPI, EAC and TCPI, then check the assumptions behind the forecasts.
"We've spent 40% of the budget and we're about 40% done." Before accepting that update, check which work the team completed and how it measured progress.
Project teams use earned value management (EVM) to compare planned work, measured progress and actual cost on the same budget basis. They can then investigate variances and forecast the cost of the remaining work. The forecast depends on their assumptions about that work.
Three numbers
- Planned value (PV) The budgeted cost of the work scheduled up to today. It comes straight from your baseline plan.
- Earned value (EV) The budgeted value of the work the team has completed, measured using the progress rule agreed for each package. A package can earn partial credit when that rule allows it.
- Actual cost (AC) Cost incurred for work performed up to today, including unfinished work. Use cost records for the same work and period as EV.
Cost can be incurred before the work earns value or its invoice is paid. Under a 0/100 progress rule, an unfinished task earns no EV yet, but its incurred cost still belongs in AC. GAO defines actual cost on that incurred-cost basis.
One more you'll need: BAC, the budget at completion, which is simply the total budget.
The example: a €200k, ten-month program
A company is replacing its warehouse management system. The budget (BAC) is €200,000 over 10 months. At the end of month 4, the project manager collects the numbers.
The plan calls for 40% of the budgeted work by now, so PV = €80,000. Finance records AC = €75,000 spent. To judge that spending, the manager also needs the value of work actually completed.
The manager calculates earned value for each package. In this example, the team has accepted the first integration milestone, which the plan assigns 20% of the package budget.
| Work package | Budget | Complete | Earned |
|---|---|---|---|
| Requirements and design | €20,000 | 100% | €20,000 |
| Data migration design | €30,000 | 100% | €30,000 |
| Build integrations | €50,000 | 20% | €10,000 |
| Testing | €40,000 | 0% | €0 |
| Training | €30,000 | 0% | €0 |
| Launch and early support | €30,000 | 0% | €0 |
| Total | €200,000 | EV = €60,000 |
The team has earned €60,000 against planned value of €80,000, at an actual cost of €75,000.
Variances and indices
Month 4
CV (cost variance) = EV − AC = 60,000 − 75,000 = −€15,000
SV (schedule variance) = EV − PV = 60,000 − 80,000 = −€20,000
CPI (cost performance index) = EV ÷ AC = 60,000 ÷ 75,000 = 0.80
SPI (schedule performance index) = EV ÷ PV = 60,000 ÷ 80,000 = 0.75
A CPI of 0.80 means the team earned 80 cents of budgeted value for each euro spent. An SPI of 0.75 means it earned three quarters of the value planned by this date. Check the underlying packages: those ratios do not measure physical quantities or identify which delay controls the finish.
Forecasting the finish
Choose an estimate-at-completion (EAC) formula that matches the evidence about the remaining work:
| If you believe… | Formula | Result |
|---|---|---|
| Current cost efficiency will continue | EAC = BAC ÷ CPI | €250,000 |
| The overrun was a one-off; the rest will go to plan | EAC = AC + (BAC − EV) | €215,000 |
| Cost and schedule pressure will both keep hurting | EAC = AC + (BAC − EV) ÷ (CPI × SPI) | €308,333 |
From the EAC you get two more useful numbers: the estimate to complete (ETC = EAC − AC = €175,000 still to spend, in the first case) and the variance at completion (VAC = BAC − EAC = −€50,000).
A study of 155 US defence contracts found that cumulative CPI had stabilised by 20% completion on 134 of them. For your own forecast, ask what would change the cost of the remaining work. If the overrun came from a one-off problem the team has already fixed, show the evidence before assuming the remaining work will come in on budget.
Is the budget still reachable?
The to-complete performance index (TCPI) asks: to finish on the original budget, how efficient does the remaining work need to be?
To-complete performance index
TCPI = (BAC − EV) ÷ (BAC − AC) = (200,000 − 60,000) ÷ (200,000 − 75,000) = 1.12
The team has achieved 0.80 and would need 1.12 for the remaining work, a 40% improvement in cost efficiency. It needs evidence of how that change will happen. GAO describes a TCPI more than 0.05 above CPI as a warning that an EAC may be optimistic. Here, TCPI tests the original budget instead. Review the remaining scope, costs and recovery options with the sponsor; the warning does not by itself authorise a new baseline.
The SPI trap, and earned schedule
For completed baseline scope, EV and PV both reach BAC, so SPI returns to 1.0 even after a late finish. Near completion, review the remaining activities and forecast dates alongside SPI.
Earned schedule fixes this by measuring schedule in time instead of money. Ask: at what point in the plan should we have earned €60,000? The plan reached €44,000 at month 3 and €80,000 at month 4, so €60,000 falls at about month 3.4.
Earned schedule
SPI(t) = earned schedule ÷ actual time = 3.44 ÷ 4 = 0.86
Forecast duration ≈ planned duration ÷ SPI(t) = 10 ÷ 0.86 ≈ 11.6 months
On this planned-value curve, earned progress sits about 0.6 months behind the status date. Continuing at the calculated time efficiency gives roughly 11.6 months instead of 10. Check that assumption against the remaining critical activities before using the forecast.
Setting up EVM on a real project
You don't need a defence contract to use it. A lightweight version needs five things:
- A work breakdown with budgets. Every work package has an owner and a budget, and together they add up to the BAC.
- A time-phased baseline. When each package is planned to be done. This gives you PV, month by month.
- Objective progress rules. Agreed up front, like the 0/100 and 50/50 rules above.
- Actual costs by work package. Timesheet codes that match the breakdown, so AC lines up with EV.
- A monthly rhythm with thresholds. For example, any CPI or SPI below 0.9 triggers a short review of cause and recovery options.
SAE's EIA-748-E revision, issued in 2026, sets out 27 guidelines, compared with 32 in the earlier version. Apply the edition and requirements in the contract. For this warehouse project, start by agreeing the five records above, then review a package whose earned value differs from its spending.
Sources
- U.S. Government Accountability Office (2020). Cost Estimating and Assessment Guide (GAO-20-195G).
- NASA (2021). Earned Value Management Implementation Handbook.
- SAE International (2026). EIA-748-E, Earned Value Management Systems.
- NDIA (2026). EVMS guide list, May 2026 Intent Guide entry. Confirms the 27 guidelines in EIA-748-E.
- Christensen, D. S. & Heise, S. R. (1993). Cost performance index stability. National Contract Management Journal, 25.
- Lipke, W., Zwikael, O., Henderson, K. & Anbari, F. (2009). Prediction of project outcome. International Journal of Project Management, 27(4).
The program and its numbers are illustrative.