EOQ explained: how much should you order?

Bigger orders mean fewer purchase orders and more stock. Calculate economic order quantity, compare practical batch sizes and see what changes when ordering gets cheaper.

Purchasing wants fewer orders. The warehouse wants smaller deliveries. Both have a cost worth understanding.

Economic order quantity, usually shortened to EOQ, is the replenishment quantity that balances ordering cost against inventory holding cost in a simple, steady-demand model.

It answers how much to order. A reorder point answers when to order. Neither question settles the other.

Put a cost on each side of the argument

Consider a fictional distributor selling 12,000 units of a standard part each year. Demand is steady, replenishment arrives as a complete batch, and shortages aren't allowed in the model.

Placing and receiving an order costs €60, regardless of its size. Holding one unit in stock for a year costs €3.

Input Symbol Example
Annual demand D 12,000 units per year
Fixed cost per replenishment S €60 per order
Annual holding cost H €3 per unit per year
Quantity in each replenishment Q The choice we're testing

The €60 needs to represent work or expense that actually changes with the number of orders. Dividing the entire purchasing department's salary by its purchase-order count doesn't establish that another order costs €60 or that removing one saves €60 in cash.

Holding cost needs similar care: capital, storage, insurance, deterioration and other relevant costs can contribute. Use a consistent annual cost per unit, with its assumptions recorded.

The two annual costs

Ordering 300 units at a time means 12,000 ÷ 300 = 40 orders a year. At €60 each, that costs €2,400.

Stock starts each cycle at 300 and falls steadily to zero. Average cycle stock is 150, so annual holding cost is 150 × €3 = €450.

Annual ordering and holding cost

Ordering cost = (D ÷ Q) × S

Holding cost = (Q ÷ 2) × H

Combined cost = (D ÷ Q) × S + (Q ÷ 2) × H

Larger batches reduce the first term and increase the second. MIT's inventory lecture develops this trade-off and the basic assumptions behind it.

Quantity per order Annual ordering cost Annual holding cost Combined annual cost
300 €2,400.00 €450.00 €2,850.00
600 €1,200.00 €900.00 €2,100.00
700 €1,028.57 €1,050.00 €2,078.57
1,200 €600.00 €1,800.00 €2,400.00

These are long-run annual rates over repeated cycles. A calculated 17.14 orders per year describes the average frequency at Q = 700, not a plan to issue a fraction of a purchase order.

Calculate EOQ, then compare usable quantities

The formula gives the minimum of that combined cost curve.

Economic order quantity

EOQ = √(2 × D × S ÷ H)

= √(2 × 12,000 × €60 ÷ €3)

= 692.82 units, approximately 693 units

At the exact mathematical minimum, ordering and holding costs are equal, about €1,039.23 each per year. The combined cost is about €2,078.46.

An order of 700 costs only about €0.11 more per year in this model. The curve is flat near the minimum. There is little reason to fight a sensible case-pack rule over that difference.

One part, long-run annual costs

Find the minimum, then check the workable sizes

Demand stays at 12,000 units/year. Holding cost stays at €3 per unit per year.

Unconstrained EOQ692.82 units€2,078.46/year

Lowest-cost feasible order693 units€2,078.46/year

OrderingHoldingCombined

Scroll the chart sideways on a narrow screen. The selected quantity and all its costs are also shown below.

Annual ordering, holding and combined cost. Minimum at 692.82 units. Selected 700 units costs €2,078.57 per year.01,0002,0003,0004,000EUR per year2006001,0001,4001,800Units per order

At 700 units: ordering €1,028.57, holding €1,050.00, combined €2,078.57 per year. Hover over the plot or use the quantity control.

This quantity meets the selected case-pack and minimum-order rules.

Selected 700 units per order, annual model costs
Order frequency17.14 orders/year
Average cycle stock350.00 units
Ordering cost€1,028.57
Holding cost€1,050.00
Combined annual cost€2,078.57
Calculation and limits

EOQ = √(2 × D × S ÷ H). Ordering cost = D ÷ Q × S. Holding cost = Q ÷ 2 × H. Feasible quantities are positive whole multiples of the selected pack, at or above the minimum. Check the feasible sizes either side of the mathematical optimum; the lowest admissible pack applies if the minimum already exceeds it.

All inputs are fictional. Demand is steady and known, price is constant, batches arrive whole and shortages are excluded. Purchase spend, safety stock, pipeline stock, discount thresholds, shelf life and capacity limits are outside this model. The selected costs are readable without the chart.

Fictional inputs: D = 12,000 units/year and H = €3/unit/year. Inspect quantities, change the fixed ordering cost, and apply a case pack or minimum order. The chart shows ordering plus holding cost, not the full purchase bill.

If the supplier requires at least 800 units in cases of 100, 800 is the lowest-cost feasible quantity on the original inputs. Its combined annual cost is €2,100, about €21.54 above the unconstrained minimum.

The calculator checks the feasible pack sizes around the minimum, subject to the minimum order. It doesn't simply round every mathematical answer upward and assume that is cheapest.

Change the ordering cost before accepting a large batch

Suppose an integration removes enough repeat handling to reduce the relevant replenishment cost from €60 to €20. EOQ falls to 400 units.

That isn't a saving claim about an installed system. It's a reason to measure what the ordering process costs and whether that cost can change.

For manufactured items, setup effort can create a similar pressure toward larger batches. Vrolen's SMED guide covers reducing changeover work while checking startup quality and displaced effort. Production replenishes over time, so a production-lot model may be needed instead of treating the entire batch as an instant delivery.

The worked changeover example shows the scheduling side of that decision. Saving setup time can support smaller batches, more output or some combination, depending on the constraint.

Keep purchase price and reorder timing separate

The chart leaves out the purchase price because annual demand and unit price are unchanged. The annual purchase bill would be D × unit price at every quantity, so adding it wouldn't change which quantity minimises cost.

A quantity discount changes that. Compare purchase cost, ordering cost and holding cost at feasible quantities, including the discount thresholds. A lower unit price can still leave a higher total cost, as the supplier comparison example demonstrates.

EOQ also doesn't tell you to wait until the shelf is empty before placing a real order. With a known positive lead time, the order needs to go out while enough stock remains to cover that wait. The safety-stock and reorder-point guide explains the timing and uncertainty side.

For components tied to a production plan, MRP adds dated requirements and existing receipts. A cheap batch size is of little use if the parts arrive after assembly.

Check the conditions before using the answer

The basic EOQ curve assumes steady known demand, a constant fixed ordering cost, a constant annual holding cost and replenishment as a whole batch. It omits shortages, quantity discounts, finite production rates and shelf-life limits.

Our cost calculation also excludes safety stock and pipeline inventory. The Q ÷ 2 term is cycle stock, not every unit the business owns.

If demand is seasonal, space is tight or the product expires quickly, compare the proposed quantity with those limits. Don't describe an infeasible mathematical minimum as the purchasing policy.

Start with the cost curve, check nearby workable quantities, then investigate the inputs that make large orders look necessary. In this example, a routine change to ordering cost matters far more than the difference between 693 and 700 units.

Sources

The demand, costs, case packs and minimum orders are fictional. Costs are modelled long-run annual amounts, not observed cash savings. The reduced-ordering-cost case assumes the €20 input has been established; no implementation cost or benefit is estimated.

NextERP vs MES vs SCADA: follow one production order

Working on something like this?

I work with operations and transformation teams on operational excellence, digital transformation programs, supply chains and industrial AI. If this sounds like your line, your program or your problem, I’d be glad to compare notes.

Abolfazl ShirkavandImage preview unavailable