Work elements stacked to different heights at three operator stations.
All notes

Continuous improvement

Yamazumi chart: balance work between operators

Stack the work elements for each operator against takt time. Use the chart to test a different work split, then check whether that sequence works on the floor.

A Yamazumi chart, also called an operator balance chart, stacks the time for individual work elements into a bar for each operator. A line across the chart marks takt time, the production pace required by demand.

The chart helps a team see where the work is uneven and which elements might move. It also keeps the discussion specific. “Station B is too slow” becomes a review of the actual tasks, sequence and conditions at B.

The Lean Enterprise Institute's definition describes this use of stacked work elements against takt. Our existing takt-time example has three stations taking 55, 75 and 50 seconds. Here, we will break those same station totals into elements to examine a proposed transfer.

Start with observed work elements

Watch representative cycles with the operators. Define where each element starts and finishes, and use the same timing basis across stations. Keep travel, material handling and checks visible.

Record variation and interruptions alongside the chart. A single fast cycle is a poor basis for assigning everyone else's work.

The table below extends the existing fictional three-station example. Its task descriptions and splits are teaching assumptions, not observations from a factory. All six elements are sequential manual work at their assigned station, with no automatic machine overlap.

Operator Work element Seconds per piece
A Prepare the part 30
A Fit the first component 25
B Assemble the next component 45
B Check and transfer 30
C Complete the final operation 35
C Final check 15

Takt is 60 seconds per piece. A's total is 55 seconds, B's is 75 and C's is 50. The average is 60, but B exceeds the required pace by 15 seconds.

Operator workloads before and after a proposed transferOriginal A 55, B 75, C 50 seconds. Proposed A 55, B 60, C 65 seconds. Takt is 60 seconds per piece.Moving 15 seconds improves the split, but C exceeds taktOriginal split302555 sA453075 sB351550 sCTakt = 60 s/pieceProposed split302555 sA451560 sB35151565 sCTakt = 60 s/pieceTotal manual work stays at 180 seconds per piece.
The same 180 seconds of manual work, before and after a proposed transfer of 15 seconds from B to C. Takt remains 60 seconds per piece.

Test a different work split

Suppose the team can split B's check-and-transfer element and move 15 seconds to C. B falls to 60 seconds, while C rises to 65. The longest station time improves from 75 to 65 seconds. The line still has a station above takt.

The transfer makes the workloads more even, but the team still needs to remove or redistribute five seconds at C to reach the 60-second pace.

With 27,000 available seconds per shift, the original longest repeat time gives an ideal rate comparison of 27,000 ÷ 75 = 360 pieces. At 65 seconds, it becomes about 415 pieces. Demand remains 450. These comparisons exclude startup, stops and rejects, just as the original takt example does.

Work split A B C Total
Original 55 s 75 s 50 s 180 s
Proposed 55 s 60 s 65 s 180 s

Three operators share 180 seconds of manual work. At a 60-second takt, that leaves no spare time if the work were divided perfectly. The arithmetic alone gives no allowance for the conditions seen during an actual shift.

Check whether a transfer is possible

Before moving the work, check access, task order, tooling and training. Determine whether the receiving operator would need extra walking or whether the transfer changes a quality check. Include those consequences in the revised times.

A stack of manual task times also cannot explain an automatic machine cycle that overlaps other work. Use a work combination chart to put those activities on a shared clock. Otherwise, adding all the durations can count the same elapsed time twice.

Vrolen's standard-work video follows an electric kettle cell through a separate example. It helps explain why timing, sequence and the stock between steps belong together.

Standard Work Explained: Same Job, Same Result, Every Shift (Lean Example) A separate electric kettle example connects the working sequence to takt. Its timings differ from the three-station example in this article.

Confirm the proposed method on the floor

Trial the new sequence with the operators and check safety, quality and repeat times. Include replenishment and interruptions in the review before treating the result as the new working method.

Keep the original chart, proposed split and observed trial results together. If the transfer introduces five seconds of walking, put those five seconds into the comparison. Update the work instructions only after the team has checked the whole sequence.

Sources and calculations

Next5W2H action plan: questions and an example

Discuss an operations problem

I work with operations and transformation teams on operational excellence, digital transformation programs, supply chains and industrial AI. Send me the problem you’re working on and the result you need.

Abolfazl ShirkavandImage preview unavailable